Baker College Administration Building


Owner:                    Baker College
Value:                      $2,200,000
Project Size:          17,500 Sq. Ft.
Date Completed:  August 2004

Project Description: This project serves as an example of a highly successful team oriented design/build project.  With classes ongoing until April of 3004, the construction of the Administration Building was limited to a 3 month construction schedule during the summer of 2004.  With classes scheduled to resume in September, various design improvements were made including modification to the structural system which allowed the total construction of the facility from excavation to interior fit out to be achieved in 48 days.